Media Summary: Alice TBM dismantle continues with its main parts lifted out of the sump using a 600 tonne crane. Footage from the Southern Approach Trench (SAT) and the SAT sump where Alice is pushed out to prepare for dismantle. Video of work activity at various locations around the Waterview

Well Connected Alliance December 2015 Timelapse - Detailed Analysis & Overview

Alice TBM dismantle continues with its main parts lifted out of the sump using a 600 tonne crane. Footage from the Southern Approach Trench (SAT) and the SAT sump where Alice is pushed out to prepare for dismantle. Video of work activity at various locations around the Waterview Watch construction of the vent stack at the Southern Ventilation Building, continuation of the permanent roads at the Northern ... Footage includes construction of the permanent road, work at the Northern Approach Trench, exterior cladding panels erected on ... Watch installation of the exterior panels to the top of the Southern Ventilation Building, removal of the temporary bridges at the ...

Key highlights include Building the southbound carriageway, laying foundations of the ventilation stack, segments transferred by ... Follow Alice TBM's big turnaround using NZ sheep grease in the Northern Approach Trench in this month's The ventilation stack of the Southern Ventilation Building is completed, at the Northern Approach Trench construction starts on the ... Watch the construction of the permanent roads at the Northern Approach Trench, the erection of external cladding to the southern ... Some of the key highlights includes construction of the three sub levels of the Southern Ventilation Building, and the Great North ... Footage of Alice TBM disappearing into the first tunnel (southbound), spoil being transferred to trucks inside the spoil building, ...

Video includes installation of culverts into the second (northbound) tunnel, construction of the temporary bridges at the Northern ... Watch footage of construction work on the Waterview Alice TBM dismantle is in full swing with its main parts lifted out of the Southern Approach sump. Footage includes roof work over the southbound carriageway, turning gantry 3 into the northbound tunnel, culvert gantry and ... Footage of the Waterview Reserve Skatepark opening in November 2016. Footage of work in the southern approach trench, Waterview Reserve skatepark and at the northern ventilation tunnel. The latter ...

Follow the preparation work for Alice TBM's relaunch in the second (northbound) tunnel. Footage of installation of work inside the Southern Approach Trench, Waterview Reserve Skatepark and Northern Ventilation ...

Photo Gallery

Well-Connected Alliance December 2015 Timelapse
Well-Connected Alliance - October  2015 Timelapse
Well-Connected Alliance December 2014 Timelapse
Well-Connected Alliance August 2015 Timelapse
Well-Connected Alliance May 2015 Timelapse
Well-Connected Alliance July 2015 Timelapse
Well-Connected Alliance February 2015 Timelapse.
Well-Connected Alliance October 2014 Timelapse
Well-Connected Alliance September 2015 Timelapse
Well-Connected Alliance June 2015 Timelapse
Well-Connected Alliance January 2015 Timelapse
Well-Connected Alliance December 2013 Timelapse
View Detailed Profile
Well-Connected Alliance December 2015 Timelapse

Well-Connected Alliance December 2015 Timelapse

Alice TBM dismantle continues with its main parts lifted out of the sump using a 600 tonne crane.

Well-Connected Alliance - October  2015 Timelapse

Well-Connected Alliance - October 2015 Timelapse

Footage from the Southern Approach Trench (SAT) and the SAT sump where Alice is pushed out to prepare for dismantle.

Well-Connected Alliance December 2014 Timelapse

Well-Connected Alliance December 2014 Timelapse

Video of work activity at various locations around the Waterview

Well-Connected Alliance August 2015 Timelapse

Well-Connected Alliance August 2015 Timelapse

Watch construction of the vent stack at the Southern Ventilation Building, continuation of the permanent roads at the Northern ...

Well-Connected Alliance May 2015 Timelapse

Well-Connected Alliance May 2015 Timelapse

Footage includes construction of the permanent road, work at the Northern Approach Trench, exterior cladding panels erected on ...

Well-Connected Alliance July 2015 Timelapse

Well-Connected Alliance July 2015 Timelapse

Watch installation of the exterior panels to the top of the Southern Ventilation Building, removal of the temporary bridges at the ...

Well-Connected Alliance February 2015 Timelapse.

Well-Connected Alliance February 2015 Timelapse.

Key highlights include Building the southbound carriageway, laying foundations of the ventilation stack, segments transferred by ...

Well-Connected Alliance October 2014 Timelapse

Well-Connected Alliance October 2014 Timelapse

Follow Alice TBM's big turnaround using NZ sheep grease in the Northern Approach Trench in this month's

Well-Connected Alliance September 2015 Timelapse

Well-Connected Alliance September 2015 Timelapse

The ventilation stack of the Southern Ventilation Building is completed, at the Northern Approach Trench construction starts on the ...

Well-Connected Alliance June 2015 Timelapse

Well-Connected Alliance June 2015 Timelapse

Watch the construction of the permanent roads at the Northern Approach Trench, the erection of external cladding to the southern ...

Well-Connected Alliance January 2015 Timelapse

Well-Connected Alliance January 2015 Timelapse

Some of the key highlights includes construction of the three sub levels of the Southern Ventilation Building, and the Great North ...

Well-Connected Alliance December 2013 Timelapse

Well-Connected Alliance December 2013 Timelapse

Footage of Alice TBM disappearing into the first tunnel (southbound), spoil being transferred to trucks inside the spoil building, ...

Well-Connected Alliance April 2015 Timelapse.

Well-Connected Alliance April 2015 Timelapse.

Video includes installation of culverts into the second (northbound) tunnel, construction of the temporary bridges at the Northern ...

Well-Connected Alliance, December 2016, Timelapse

Well-Connected Alliance, December 2016, Timelapse

Watch footage of construction work on the Waterview

Well-Connected Alliance November 2015 Timelapse Video

Well-Connected Alliance November 2015 Timelapse Video

Alice TBM dismantle is in full swing with its main parts lifted out of the Southern Approach sump.

Well-Connected Alliance March 2015 Timelapse

Well-Connected Alliance March 2015 Timelapse

Footage includes roof work over the southbound carriageway, turning gantry 3 into the northbound tunnel, culvert gantry and ...

Well-Connected Alliance, November 2016, Timelapse

Well-Connected Alliance, November 2016, Timelapse

Footage of the Waterview Reserve Skatepark opening in November 2016.

Well-Connected Alliance, October 2016, Timelapse

Well-Connected Alliance, October 2016, Timelapse

Footage of work in the southern approach trench, Waterview Reserve skatepark and at the northern ventilation tunnel. The latter ...

Well-Connected Alliance November 2014 Timelapse.

Well-Connected Alliance November 2014 Timelapse.

Follow the preparation work for Alice TBM's relaunch in the second (northbound) tunnel.

Well-Connected Alliance May 2016 Timelapse

Well-Connected Alliance May 2016 Timelapse

Footage of installation of work inside the Southern Approach Trench, Waterview Reserve Skatepark and Northern Ventilation ...