Media Summary: We are going to talk about what are we going to do during the Flight Readiness Review for the LAS 25DA rocket vehicle. Please ... The Flight Readiness Review for the LAS 25DA VTOL flight was postponed for August 17th, 2020, although initially it was ... In this final part of What is Flight Readiness Review mini-series we are talking about the Ground Support Equipment (GSE).

Mission 9 Sitrep 16 Roll Thrusters Integration - Detailed Analysis & Overview

We are going to talk about what are we going to do during the Flight Readiness Review for the LAS 25DA rocket vehicle. Please ... The Flight Readiness Review for the LAS 25DA VTOL flight was postponed for August 17th, 2020, although initially it was ... In this final part of What is Flight Readiness Review mini-series we are talking about the Ground Support Equipment (GSE). We are talking avionics and heating system that are going to be checked during the Flight Readiness Review. Please support this ... The LAS 25DA was lifted in the Dynamic Test Stand in vertical position. The tank was connected with the engine. The LAS 25DA Flight Readiness Review (FRR), scheduled for August 8th, 2020. After that date, assuming that the FRR will be ...

A heating element and the coil from the venting valve were not working properly and the team disconnected the tank from the ... The team completed the work on the power connections. The sensors The LAS 25DA engine was brought to the DTS. The connection between the tank and the engine will follow. Please support this ... In a previous episode we were talking about two defects that were identified on the LAS 25DA vehicle. One of them related to a ... The Launch Assist System is allowing the reduction of polluting propellant for orbital launches between 20-50%. And this while ... Nicu is checking the electric connections in the electric panel through which the electric power is delivered to the rocket. Please ...

We held the second day of the Flight Readiness Review (FRR), dedicated to the electrical system, in the Flight Command and ... In this video we are explaining how the first VTOL flight is going to happen. Please support this video series on Patreon: ... After the tank leakage problem that we encountered in the first test in the Dynamic Test Stand, we decided to replace the tank.

Photo Gallery

MISSION 9 - SITREP 16: Roll Thrusters Integration
MISSION 9 - SITREP 6: Roll Control Thrusters
MISSION 9 - SITREP 24: What is Flight Readiness Review - Part I
MISSION 9 - SITREP 23: Flight Readiness Review Postponed for August 17th
MISSION 9 - SITREP 26: What is Flight Readiness Review - Part III
MISSION 9 - SITREP 25: What is Flight Readiness Review - Part II
MISSION 9 - SITREP 11: LAS 25DA in Vertical Position
MISSION 9 - SITREP 17: Flight Readiness Review Scheduled for August 8th
MISSION 9 - SITREP 12: LAS 25DA Service Operations
MISSION 9 - SITREP 19: Power Connections Complete
MISSION 9 - SITREP 10: The LAS 25DA Engine Brought to the DTS
MISSION 9 - SITREP 1: Introduction
View Detailed Profile
MISSION 9 - SITREP 16: Roll Thrusters Integration

MISSION 9 - SITREP 16: Roll Thrusters Integration

The

MISSION 9 - SITREP 6: Roll Control Thrusters

MISSION 9 - SITREP 6: Roll Control Thrusters

The

MISSION 9 - SITREP 24: What is Flight Readiness Review - Part I

MISSION 9 - SITREP 24: What is Flight Readiness Review - Part I

We are going to talk about what are we going to do during the Flight Readiness Review for the LAS 25DA rocket vehicle. Please ...

MISSION 9 - SITREP 23: Flight Readiness Review Postponed for August 17th

MISSION 9 - SITREP 23: Flight Readiness Review Postponed for August 17th

The Flight Readiness Review for the LAS 25DA VTOL flight was postponed for August 17th, 2020, although initially it was ...

MISSION 9 - SITREP 26: What is Flight Readiness Review - Part III

MISSION 9 - SITREP 26: What is Flight Readiness Review - Part III

In this final part of What is Flight Readiness Review mini-series we are talking about the Ground Support Equipment (GSE).

MISSION 9 - SITREP 25: What is Flight Readiness Review - Part II

MISSION 9 - SITREP 25: What is Flight Readiness Review - Part II

We are talking avionics and heating system that are going to be checked during the Flight Readiness Review. Please support this ...

MISSION 9 - SITREP 11: LAS 25DA in Vertical Position

MISSION 9 - SITREP 11: LAS 25DA in Vertical Position

The LAS 25DA was lifted in the Dynamic Test Stand in vertical position. The tank was connected with the engine.

MISSION 9 - SITREP 17: Flight Readiness Review Scheduled for August 8th

MISSION 9 - SITREP 17: Flight Readiness Review Scheduled for August 8th

The LAS 25DA Flight Readiness Review (FRR), scheduled for August 8th, 2020. After that date, assuming that the FRR will be ...

MISSION 9 - SITREP 12: LAS 25DA Service Operations

MISSION 9 - SITREP 12: LAS 25DA Service Operations

A heating element and the coil from the venting valve were not working properly and the team disconnected the tank from the ...

MISSION 9 - SITREP 19: Power Connections Complete

MISSION 9 - SITREP 19: Power Connections Complete

The team completed the work on the power connections. The sensors

MISSION 9 - SITREP 10: The LAS 25DA Engine Brought to the DTS

MISSION 9 - SITREP 10: The LAS 25DA Engine Brought to the DTS

The LAS 25DA engine was brought to the DTS. The connection between the tank and the engine will follow. Please support this ...

MISSION 9 - SITREP 1: Introduction

MISSION 9 - SITREP 1: Introduction

As

MISSION 9 - SITREP 14: Resistor and Coil Defects Clarifications

MISSION 9 - SITREP 14: Resistor and Coil Defects Clarifications

In a previous episode we were talking about two defects that were identified on the LAS 25DA vehicle. One of them related to a ...

MISSION 9 - SITREP 4 - Our Goal: Spaceflight Sustainability

MISSION 9 - SITREP 4 - Our Goal: Spaceflight Sustainability

The Launch Assist System is allowing the reduction of polluting propellant for orbital launches between 20-50%. And this while ...

MISSION 9 - SITREP 18: Electric Panel Connections to the Rocket

MISSION 9 - SITREP 18: Electric Panel Connections to the Rocket

Nicu is checking the electric connections in the electric panel through which the electric power is delivered to the rocket. Please ...

MISSION 9 - SITREP 22: Pitch & Yaw Vehicle Control

MISSION 9 - SITREP 22: Pitch & Yaw Vehicle Control

In the previous episodes we saw how the

MISSION 9 - SITREP 34: FRR in the FCCC

MISSION 9 - SITREP 34: FRR in the FCCC

We held the second day of the Flight Readiness Review (FRR), dedicated to the electrical system, in the Flight Command and ...

MISSION 9 - SITREP 36: First Flight, What to Expect

MISSION 9 - SITREP 36: First Flight, What to Expect

In this video we are explaining how the first VTOL flight is going to happen. Please support this video series on Patreon: ...

MISSION 9 - SITREP 39: New Tank

MISSION 9 - SITREP 39: New Tank

After the tank leakage problem that we encountered in the first test in the Dynamic Test Stand, we decided to replace the tank.